Fitch cuts LAX people mover bonds four notches as opening slips
latimes.com

Fitch cuts LAX people mover bonds four notches as opening slips

Archived — this story has rotated out of today’s deck. It is kept here in full.

The gist

Fitch Ratings cut the rating on $1.2 billion in LAX people mover bonds from BB to B-.
The $3.3 billion train is years late, and repeated test restarts are the crux.

Background

The Automated People Mover, also called SkyLink, is a 2.25-mile train meant to shuttle travelers between terminals, parking lots, the LAX/Metro Transit Center and a new rideshare lot, and is the most-anticipated feature of the airport's $30 billion overhaul. It is being built by LINXS (LAX Integrated Express Solutions), a private-public partnership formed in 2018 that includes Fluor, Balfour Beatty, Alstom Transport USA, ACS Infrastructure Development, HNTB and Dragados USA, under the city agency LAWA (Los Angeles World Airports). The $3.3 billion train was initially slated to open in 2023 and is now three years behind schedule and more than $1 billion over its original construction budget. To open, it must pass 30 days of consecutive testing without substantial issues and get sign-off from the airport and an outside assessor — a period that has kept restarting.

How it unfolded

  1. recentlyThe $3.3 billion train, initially slated to open in 2023, is now three years behind schedule and more than $1 billion beyond its original construction budget.
  2. recentlyThe 30-day consecutive testing period required before opening, plus sign-off from the airport and an outside assessor, has continued to restart.
  3. Nov 7, 2026An Airbus A350-900 flying as Air France Flight AF28 made an unauthorized sharp left turn after takeoff from LAX runway 24L, crossing the route of a recently departed American Airlines flight.
  4. Nov 12, 2026Fitch Ratings downgraded the LINXS Skylink people mover project, cutting the rating on $1.2 billion in bonds four notches from BB to B- since July.
  5. Nov 12, 2026The contractor said the train won't be ready until February 2027 — or even later.

Key terms

bonds
The return an investor earns from holding a bond, usually expressed as a percentage of its price.
people mover
A small-scale automated transit system serving limited areas such as airports, downtown districts or theme parks.
private-public partnership
A long-term arrangement in which a government and private firms share financing and operation of public infrastructure projects.

Source: Wikipedia

Who’s saying what

Official
LINXS spokesperson said the consortium remains committed to working with LAWA to deliver the Automated People Mover and provide a world-class transportation system for the Los Angeles region.
Caution
Lehman said that each time there's a path towards opening, there's a setback.
Analysts
Fitch Ratings cut the bonds four notches to B-, reflecting the project's mounting risk as a key deadline nears.