False smoke alarm nearly floods Jane Street NYC datacenter
zenfs.com

False smoke alarm nearly floods Jane Street NYC datacenter

Archived — this story has rotated out of today’s deck. It is kept here in full.

The gist

Jane Street's Michael Bacarella says contractor dust set off a smoke alarm that stopped datacenter cooling.
The account shows how close the firm keeps servers to its trading floor.

Background

Jane Street is the trading firm whose Manhattan datacenter at 1 New York Plaza was affected; Michael Bacarella is a member of its systems team who wrote the account. The firm kept its machine room next to its trading floor, and the room grew from a small setup into a datacenter with about 10 rows of server cabinets as the firm went from 10 people to 150. Bacarella says the proximity was meant to protect servers and trading strategies from theft and to let automated trading systems be shut down by pulling power cables. He published the account on Nov 10, 2026, and LavX News summarized it two days later.

How it unfolded

  1. date unknownContractors cutting material in a prep room next to the datacenter kicked up dust that set off the smoke alarm.
  2. date unknownThe alarm shut down the CRAC units (computer-room air conditioners), and the sprinkler pipes above the room filled with pressurized water.
  3. date unknownThe Hong Kong office called Bacarella after someone saw many servers report rising temperatures; he ran down Water Street, took an elevator to the 33rd floor and pulled power cables row by row and cabinet by cabinet.
  4. date unknownAfter he cut power, the temperature monitor read 141 F, 142 F, 143 F, 143.5 F and 143.6 F, then stopped.
  5. date unknownMajor New York markets had closed for the day, and the firm restored service the next morning.
  6. date unknownFollow-up meetings focused on the failure; Jane Street kept the sprinklers, tightened procedures and surveillance, and continued to host servers in the office building next to the trading floor.
  7. Nov 10, 2026Bacarella publishes his account of the incident.
  8. Nov 12, 2026LavX News publishes an article summarizing Bacarella's account.

Key terms

CRAC units
Cooling equipment that removes waste heat from computer hardware to keep components within safe temperature limits.
sprinkler heads
The component of a fire sprinkler system that releases water when fire or high temperature is detected.

Source: Wikipedia

Who’s saying what

Expert
Bacarella says the dust from contractors' cutting set off the alarm, cooling stopped, and he ran across Lower Manhattan to cut power before heat opened the sprinkler heads.
Official
Bacarella says Jane Street kept its machine room close to its trading floor to protect servers and trading strategies from theft and to allow automated trading systems to be shut down by pulling power cables.

Still unverified

The sources describe the infrastructure as "2011-era" but give no exact date for the incident.